The Effect of Project Management Information System on

Project Managers and Project Success

Shadi Fallah ; Yousef Gholipour-Kanani

Department of management, Islamic Azad University, Qaemshahr, Iran

shfallaah@gmail.com

Department of Industrial Engineering, Islamic Azad University, Qaemshahr, Iran

gholipourkanani@yahoo.com

Abstract. Project management information

system (PMIS) helps managers in decision

making, planning, organizing and controlling

the project. Based on the importance of

decision making, the aim of this study is

assessing the effects of PMIS on the project

management success. This study designed a

comprehensive model to evaluate the impact of

PMIS on the project management functions.

This model included five factors such as: PMIS

quality, the quality of output information of

PMIS, PMIS application, PMIS impact on

project management and the impact of PMIS

on the project success. This study conducted in

Iran in three dependent firms in Tehran

petroleum. Data of this research is collected by

using questionnaires from project managers.

Results demonstrated the crucial role of PMIS

on the project management success due to

better planning, proper scheduling, regulating

and controlling the project. At the end

limitation and suggestion for future study is

discussed.

Keywords: Project management information

system, decision making, planning, project

control.

INTRODUCTION

Information is one of the most important

capitals in the organizations, because all

physical facilities and environmental

decision making are affected by

information. Information can change

competitive aspects withing the

organization and lead to competitive

advantage. Morever, successful

organizations in information technology

can change competition characteristics in

the industry and benefit by being pioneer.

Due to the importance of project

management information system (PMIS) to

implement project faster, less expensive

and with higher quality, the general

expectation from project managers

enhanced (Welsch, 2006). Organizations

apply information systems in their

organizations to improve effeciency and

profitibility; through this way they can

adopt themselves easier to environmental

changes and attain updated information.

Also managers can estimated the project

costs, profits and budget by using PMIS.

In general, PMIS can be used in

Implementing activities, goods and

materials management, collecting and

classifying financial and non-financial

information, and storage of information.

Despite of the importance of PMIS, there

are still limited studies in this filed.

Previous studies mostly considered on

implementing information technology

instruments in the organizations. Morever,

due to importance of oil and gas projects

more research about PMIS is needed.

Because, in this industry PMIS can play

the key role in recognizing the suitable

resources, planning and scheduling, this

study has considered on the effect of

project management information system on

project managers and project success.

Forasmuch as PMIS accompanies

managers in all process of implementing

Page 2 of 6

Journal for Studies in Management and Planning

Available at http://edupediapublications.org/journals/index.php/JSMaP/

e-ISSN: 2395-0463

Volume 02 Issue 4

April 2016

Available online: http://edupediapublications.org/journals/index.php/JSMaP/ P a g e | 73

project, this study aims to assess the effect

of PMIS on project managers. Also this

study targeted to evaluate the effect of

PMIS on project success. Furthermore, the

effects of PMIS on its application, project

management characteristics and quality of

outputs.

LITERATURE RIVIEW

An information system defined as ‘’ a set

of related components that assist to collect,

recovery, processing, storage and

distribution of information within the

organization’’ (Olson, 2004). This

information is very useful for decision

making and controlling the operation in an

organization. Managerial team can use this

information for analysis and making

decision about future product line. Also

Management information system defined

as ’’ series of tools which provide to

managers the required information in their

professional fields on time, accurate and in

appropriate conditions’’. Study of Welsch

(2006) indicated that MIS assists middle

managers through the provision of

information in appropriate formats

according to what they need.

According to Olson (2004) projects due to

their diverse and uniqueness are

structurally different from the current

organizational routines. Project

management is always more difficult than

regular administration and requires more

attention to different aspects of

organization. The project combines the

demands of the custodians, contractors and

other stakeholders; so to create unity

between all factors involved in the project,

appropriate techniques and utilities should

be exploited (Baker et al., 2009). Belout

(2003) in an empirical study considered on

the effects of PMIS on multi-project

environment. Results showed that using

project management information system is

beneficial for project managers. However,

no adverse effects have been observed due

to the project, and information overload.

Commonly projects implement in certain

time, cost and quality; they mostly done

only for one time. Therefore it is essential

to apply an instrument which helps

organization to do projects more effective

(Dietrich and Lehtonen, 2005). Also

another study has investigated the

Challenges in information systems projects

(Finch, 2003). Adams and Barndt (2008) in

their study showed that PMIS has a

positive effect on the management and

execution of construction projects and

managers should give careful consideration

to overcome the weaknesses of the project.

According to study of (Cooper et al., 2001)

during the projects some changes may

happen in process. Despite the theoretical

accuracy in the preparation of plans and

administered programs, managers should

carefully pay attention to using on time and

accurate information. Also project control

team requires different expertise to

accomplish the responsibilities as good as

possible (Dai and Wells, 2004). For the

purpose of control, various units should

send information to control project

department under proper discipline and

coordination. Particularly, the activities

which locate on the critical path of the

project should regularly monitor and

inspect to ensure that occurred delays don’t

lead to delay in entire project. Bozeman

and Kingsley (2007) showed that data

quality of PMIS is related positively to the

correct decisions, managers' satisfaction

from PMIS and increasing usage of PMIS

within the organization. Also this study

discussed about implementing multiple

Page 3 of 6

Journal for Studies in Management and Planning

Available at http://edupediapublications.org/journals/index.php/JSMaP/

e-ISSN: 2395-0463

Volume 02 Issue 4

April 2016

Available online: http://edupediapublications.org/journals/index.php/JSMaP/ P a g e | 74

projects simultaneously causes that the

project managers expand the results of the

quality information for a project to all

existing projects. Based on

abovementioned literatures the following

hypotheses were proposed:

H1. PMIS quality is positively related to

output information quality.

H2. PMIS quality is positively related to

PMIS application and project management

factors.

H3. Output information quality of PMIS is

positively related to PMIS application and

project management factors.

H4. PMIS application influences positively

on project management factors.

H5. PMIS application influences positively

on project success factors.

H6. Project management factors influences

positively on project success.

METHODOLOGY

Data of this research attained by

distributing questionnaire which included

20 questions based on 6 main categories.

This study targeted project control

department of three firms which dependent

to Tehran Petroleum Company. Targeted

employees were 80 and all of them

participated in this research. According to

table of Morgan number of participants is

63. This study applied SPSS to test

normality of study population and

hypothesized relationships. Testing

normality of population evaluated by using

Kolmogorov–Smirnov test; also binominal

test applied to assess the hypothesized

relationships.

To consider on validity of questionnaire,

all questions reviewed by several scholars

and their opinions applied in the study

instrument. After discussion and making

some changes, the validity of questionnaire

approved by them. To test reliability of

questionnaire, this study applied Cronbach’

alpha and all values ranged between .76

and .85; Therefore, result demonstrated the

reliability of questionnaire. Scale format of

questionnaire was based on five-point

Likert scale (1=very low to 5=very high).

Table 1. Respondents information

Number Percentage

Gender:

Male 51

81%

Female 12 19%

Total 63 100%